Export MPAN: what it is and how to get one for your solar panels

An export MPAN is the 13-digit number for the point where your home sends electricity onto the grid. You need one to be paid for the solar power you export under the Smart Export Guarantee. Your export supplier usually asks your network operator for it when you apply, and Octopus says it usually takes one to four weeks.

Written by the SolarSave team

Updated Checked against 12 sources

We install solar panels and batteries and send the network paperwork for our customers. We don't issue MPANs or run export tariffs: network operators and energy suppliers do. SolarSave is an Octopus Energy Trusted Partner, but Octopus doesn't pay us anything.

In short

  • It's a different number from the import MPAN on your electricity bill.
  • Your network operator creates it. Your export supplier normally asks for it.
  • Suppliers such as Octopus ask for your MCS certificate and your network operator's letter or email, so have them ready.
  • If a supplier asks for "your G98 or G99", it may really want your network operator's acceptance letter.
Import and export MPANs at a glance
Import MPANExport MPAN
What it identifiesWhere electricity comes into your homeWhere your solar electricity goes out to the grid
Where you find itYour electricity bill or accountYour export supplier's account, once it's set up
Who uses itThe supplier you buy electricity fromThe supplier that pays you for exports
Length13 digits (21 in the full grid)13 digits (21 in the full grid)

What is an export MPAN?

MPAN stands for meter point administration number. An export MPAN is the one for the electricity your home sends out to the grid, and it's separate from your import MPAN.

  • 13 digits. The full number has 21 characters, set out in a grid. The bottom 13 digits are the core number, and most forms only ask for those.
  • The first two digits name your network. They're the distributor ID of the company that runs your local power network, your distribution network operator (DNO).
  • You need it to be paid. Ofgem's guidance says you need an export MPAN to be paid under the Smart Export Guarantee.
A smart meter on a house wall with one cable to a pylon, with arrows showing electricity flowing both ways along it
Illustration. One connection, two meter points: electricity in and electricity out are counted separately.
What the first two digits mean in the areas we cover most
First two digitsAreaNetwork operator
11East MidlandsNational Grid Electricity Distribution
14West MidlandsNational Grid Electricity Distribution
15North East EnglandNorthern Powergrid
16North West EnglandSP Electricity North West
23YorkshireNorthern Powergrid

Not sure which is yours? Check your postcode on the Energy Networks Association's site.

Do you need an export MPAN?

Only if you want to be paid for the electricity you export. Your panels work without one: you still use your own solar power at home. You just aren't paid for what goes out.

To be paid under the Smart Export Guarantee, Ofgem's guidance says you need two things:

  • An export MPAN.
  • A meter that can take half-hourly readings, fitted where your home connects to the network. GOV.UK says that's typically a smart meter.

Read how the scheme works in our guide to the Smart Export Guarantee.

Is an export MPAN created automatically?

Not usually. Octopus says an export MPAN isn't automatically assigned to your home: it's created for your solar or battery system. A 2026 Welsh Government technical note, written for premises in Wales, says network operators issue one automatically once a system that can export is confirmed as meeting the connection rules. In practice it varies:

  • SP Electricity North West says that for exports up to 30 kW, its approval letter can go to your energy supplier for an export tariff. Over 30 kW, you need to request an export MPAN.
  • SSEN runs the networks in central southern England and the north of Scotland. It says it doesn't insist on export MPANs under 30 kW. You can still ask for one through your energy supplier.

So don't wait for one to turn up. Apply for an export tariff, and the supplier can ask for the number if you don't have it.

How do you get an export MPAN?

Through your export supplier. These are Octopus's steps, with a meter check from Ofgem's rules added as step 2.

  1. Get your paperwork from your installer. Octopus asks for your MCS certificate and a letter or email from your network operator confirming it has been notified of your system.
  2. Check your meter. It needs to take half-hourly readings. If you don't have a smart meter, ask your energy supplier about one.
  3. Choose an export tariff and apply. You apply to the supplier, on its own form. Ofgem says it doesn't have to be the supplier you buy electricity from. Compare rates in the best SEG tariffs.
  4. The supplier asks your network operator for the number. Octopus contacts the network operator for you to request a new export MPAN for your home.
  5. The network operator creates it, and the supplier registers it. The supplier then starts reading your exports from your meter.
Paperwork travels from a house with solar panels to an energy supplier's office, then on to the local electricity network's substation, and a reply comes back to the house
Illustration. You apply to the supplier, the supplier asks the network operator, and the number comes back.

You can only be on one Smart Export Guarantee tariff at a time.

An inverter and a red isolator switch fixed high on a brick wall under a concrete canopy
The inverter on a house we fitted in Newark (NG24), July 2026.

Thinking about solar or a battery?

We fit MCS certified systems and send the network notice for you. Our entry system is fully installed from £7,500, including VAT: 10 panels, a Fox ESS battery and scaffolding to one side. You get a free written quote, with no pressure to sign.

We'll check we cover your area

Who should we send your quote to?

Or call 0333 577 6576, Monday to Friday, 9am to 5pm. We'll only use your details for your quote. Privacy policy

How long does it take to get an export MPAN?

Octopus says it usually takes one to four weeks from when it asks your network operator, and that the timing is out of its hands. If a document is missing, the supplier can't make the request, so have everything ready on the day you apply.

Don't leave it for months. The Welsh Government's note says an export MPAN that stays unregistered for a year or more may become void, and you'd then need to apply to your network operator for a new one.

Where can you find your export MPAN?

  • In your export supplier's account. On Octopus, once your export tariff is set up, a second "Electricity" section on your online dashboard shows your export MPAN.
  • Probably not on your electricity bill. The number in the box there is your import MPAN.
  • Ask your export supplier. If it hasn't set one up yet, it can ask your network operator for you.

What if your export MPAN is delayed or refused?

Here are four hold-ups and what to do about each.

  • The supplier asks for "your G98 or G99". National Grid Electricity Distribution says suppliers may ask for this by mistake. What they need is a DNO acceptance letter, which confirms your system was reported and accepted. Ask your installer first. If your network is National Grid's and your panels are already fitted, you can also request one online.
  • Your network operator was never told about the system. For a G98 system, MCS says the network operator must be told within 28 days of switch-on. Bigger G99 systems need its permission before they connect. Ask your installer for a copy of the notice, and see G98 vs G99.
  • Your installer has stopped trading. You can deal with the network operator yourself. The Welsh Government's note says network operators provide new MPANs at the request of a supplier or the site owner.
  • You don't have an MCS certificate. Octopus says it's one of the few suppliers that will pay for exports without MCS or Flexi-Orb certification. You must also buy your electricity from Octopus, it charges £250, and it asks for an electrical installation certificate, a building regulations certificate and a DNO acceptance letter.

Does your installer get the export MPAN for you?

Usually your export supplier asks for it, not your installer. Your installer's part is to tell the network operator about your system and issue your MCS certificate.

We send that notice for our customers within 7 working days, and email your handover pack with your certificates. See what happens on installation day and what an MCS certificate is.

The bottom line

Get your MCS certificate and your network operator's letter or email from your installer, then apply for an export tariff. The supplier asks for your export MPAN, and Octopus says it usually takes one to four weeks.

Questions people ask

How many digits is an export MPAN?

The core number is 13 digits. The full version, set out in a grid, has 21 characters, but most forms only ask for the 13.

Is an export MPAN the same as my import MPAN?

No. Ofgem's guidance says the export MPAN is different from the MPAN for the electricity you buy.

Who issues an export MPAN?

Your network operator, the company that runs the local power network. Your export supplier usually asks for it for you.

How long does an export MPAN take?

Octopus says it usually takes one to four weeks once it has asked your network operator.

Can I be paid for exports without an export MPAN?

Not under the Smart Export Guarantee. Ofgem's guidance says you need one to be paid under it.

Do I need a new meter for an export MPAN?

Not if your meter can already take half-hourly readings, fitted where your home connects to the network. GOV.UK says that's typically a smart meter. If you don't have one, ask your energy supplier.

What if my supplier asks for my G98 or G99?

National Grid Electricity Distribution says it may really want a DNO acceptance letter, confirming your system was reported and accepted. Ask your installer first. National Grid also lets you request one online.

Can an export MPAN expire?

It can. A Welsh Government technical note says one left unregistered for a year or more may become void, and you'd then need to apply for a new one.

About this guide

Written by the SolarSave team in Retford: MCS certified installers, led by a founder in solar since 2010. We checked this against Ofgem's Smart Export Guarantee guidance, the Welsh Government's technical note, Octopus Energy, National Grid Electricity Distribution, SP Electricity North West, SSEN, National Grid, MCS and GOV.UK on 28 November 2026. Processes change from time to time, so we recheck this page when they do.

The 12 sources we checked
  1. Ofgem: Smart Export Guarantee, guidance for generators (paragraphs 1.8, 1.17, 1.18 and 1.22 to 1.24), December 2019, checked 28 November 2026
  2. Welsh Government: Connecting on-site generation to the grid, technical note, first published 2 June 2026, updated 11 September 2026, checked 28 November 2026
  3. Octopus Energy: How do I get an export MPAN?, checked 28 November 2026
  4. Octopus Energy: What is an MPAN?, checked 28 November 2026
  5. Octopus Energy: Export without MCS, checked 28 November 2026
  6. National Grid Electricity Distribution: DNO acceptance letter request FAQs, checked 28 November 2026
  7. SP Electricity North West: G99 applications (export MPANs over 30 kW), checked 28 November 2026
  8. SSEN: MPAN process for microgeneration customers (REF-PS-066 Rev 2.0), 2025, checked 28 November 2026
  9. MCS: Notifying DNOs, updated 14 July 2026, checked 28 November 2026
  10. National Grid: Who is my distribution network operator? (distributor IDs), checked 28 November 2026
  11. Energy Networks Association: Find my network operator, checked 28 November 2026
  12. GOV.UK: Smart Export Guarantee (meter for export), checked 28 November 2026

Questions about exporting your solar power?

Ask us before you commit. We'll explain what paperwork your system comes with and what to do with it.

Prefer to talk? Call 0333 577 6576, Monday to Friday, 9am to 5pm.

Who you'll deal with

  • JamesFounder and Sales Director, in solar since 2010
  • StephanieOffice Manager, in solar since 2013
  1. Step 1
  2. Step 2

Get My Free Solar Quote

Get a quote and we'll help calculate how much you could save.

We'll check we cover your area

Who should we send your quote to?

Google
reviews
5.0

Rated 5 out of 5
by our customers on Google

We'll only use your details for your quote. Privacy policy